Work commenced on 13th November 2011 to remove Royal Mail's disused conveyor that links the three island platforms at East Croydon to the adjacent sorting office on the south east side of the station. Lester Hayes visited on 18th November, and whilst the structure was still largely complete, saw the early stages of the demolition. |
![]() |
(above) By the 18th November removal of cladding had started on the tower on platforms 1 & 2.
(left) This shot shows how the conveyer runs above the buildings on platforms 5 & 6. |
![]() |
Seen from the north end of platforms 5 & 6, how the conveyor snakes from platforms 1 & 2 (extreme right), over platforms 3 & 4, then along platforms 5 & 6 until it turns left into the sorting office can clearly be seen. |
![]() |
The snaking conveyor as seen from Billinton Hill at the south end of the station. |
![]() |
The conveyor leaves the station and crosses Billinton Hill to provide direct access to the sorting office (on the left). The major demolition will take place between the early hours of Christmas Day and the early hours of December 27th 2011. It will be replaced by a new footbridge which will eventually link the Ruskin Square and Lansdowne Road developments. |
|
|
||
This feature is brought to you by the Southern Electric Group as a service to its members and enthusiasts. The Southern Electric Group is the only group covering all aspects of the Southern Electric System past , present and future. If you are not a member you are very welcome to join the group. For more details please follow the links bottom left.
|
||
| Find out more about the SEG or about
membership and to print out a membership application form. |
This page updated 14th January 2012 by Colin Duff. All text, graphics and photographs are ©Copyright |
|